Splatsin Homes Show Home Construction Progress

Splatsin Development Corporation (SDC) is proud to share continued progress on the new Splatsin Homes show home in Enderby on Vernon Street. It’s exciting to see the vision steadily coming to life.

On February 17, the SDC construction team completed the forming and pouring of the strip footings for the ICF foundation — a critical first step in building a strong, durable structure from the ground up.

By February 24, installation of the ICF (Insulated Concrete Form) basement walls was nearing completion, with the final rows placed ahead of the concrete pour. These ICF blocks are assembled, reinforced with rebar, and filled with concrete to create a high-performance, energy-efficient foundation system. The result is exceptional strength, superior insulation, and long-term durability — key features of the Splatsin Homes building approach.

Once poured, these walls will form the solid base of the home as construction continues above grade and the full structure begins to take shape.

Each stage reflects SDC and Splatsin Homes' commitment to quality construction, innovation, and building homes designed to stand the test of time.

Stay tuned for more updates as work continues on Vernon Street.

Learn more about Splatsin Homes: https://www.splatsinhomes.com/

Previous
Previous

Shuswap North Okanagan Rail Trail Update

Next
Next

Splatsin Homes Showhome Groundbreaking Marks Major Milestone in Community Housing